New TopShim run:

version = topshim 2.4.0
date = 2026-11-03
time = 16:46:13.709
command = topshim  convcomp ordmax=4

FINE SHIMMING

Parameters:

probe = Z104275_0310
solvent = CDCl3
shim nucleus = 2H
nucleus optimised for = 1H
o1p (from lock) = 7.24 ppm

Results:


1D Shimming:
Low S/N encountered. The acquisition parameters will be changed to improve this issue.
Iteration  1: FWHM Before= 0.3 Hz, Target= 0.2 Hz, After= 0.5 Hz
Iteration  2: FWHM Before= 0.5 Hz, Target= 0.2 Hz, After= 0.3 Hz
Iteration  3: FWHM Before= 0.3 Hz, Target= 0.5 Hz
Shim succeeded

Lineshape quality factor (1D spectrum, spinning) = 0.599

shim changes: 
Z	+74
Z2	+78
Z3	+3
Z4	+222

duration = 2 min 15 sec
completed successfully
finished Tue Nov 03 16:48:27 2026


========================================================================