New TopShim run:

version = topshim 2.4.0
date = 2026-10-21
time = 22:22:42.080
command = topshim  convcomp ordmax=4

FINE SHIMMING

Parameters:

probe = Z104275_0310
solvent = CDCl3
shim nucleus = 2H
nucleus optimised for = 1H
o1p (from lock) = 7.24 ppm

Results:


1D Shimming:
Low S/N encountered. The acquisition parameters will be changed to improve this issue.
Iteration  1: FWHM Before= 0.3 Hz, Target= 0.3 Hz, After= 0.9 Hz
Iteration  2: FWHM Before= 0.9 Hz, Target= 0.2 Hz, After= 0.5 Hz
Iteration  3: FWHM Before= 0.5 Hz, Target= 0.3 Hz, After= 0.3 Hz
Shim succeeded

Lineshape quality factor (1D spectrum, spinning) = 0.484

shim changes: 
Z	+462
Z2	+663
Z3	+1814
Z4	+3447

duration = 2 min 45 sec
completed successfully
finished Wed Oct 21 22:25:25 2026


========================================================================